New Rapid Clinical Manufacturing Facility, Cork, Ireland

STS was appointed as the E&I contractor for a US Blue-chip Multinational Client in building a new Rapid Clinical Manufacturing Facility (RCMF). The project consisted of three main areas including production facilities, the necessary technical ancillary rooms and offices. The E&I scope of work included the following:​

  • LV Installation ​
  • MCC Installation ​
  • UPS Installation ​
  • Calibration of Instruments ​
  • Fire Alarm Supply & Installation ​
  • Gas Detection Supply & Installation ​
  • Security & Access Control Supply & Installation ​
  • Door Interlocking System Supply & Installation ​
  • Comms Supply & Installation ​
  • Public Address Supply System & Installation ​
  • General Services Installation ​
  • Commissioning​

Quick Facts

Duration
12 months
Team
SISK
Nature of Facility
Pharmaceutical
Peak Labour
250