Merck, K2 Project, Cork, Ireland

STS was appointed as the electrical and instrumentation contractor for Merck’s K2 project. The main portion of the development consists of installing a new air casting machine ‘K2’ to manufacture Hi-Flow membrane at its Carrigtwohill facility. STS scope of services covered the following:

  • Containment
  • Main Distribution
  • Sub-Mains Distribution
  • General Power
  • Lighting Installation
  • Motive Power
  • Instrumentation & Controls
  • Fire Alarm Installation
  • Gas Detection System
  • Lightning Protection
  • Communications
  • Heat Tracing
  • Access Control
  • Instrument & Controls
  • Earthing & Bonding
  • BIM

 

 

Quick Facts

Duration
12 Months
Team
Callaghan Engineering
Nature of Facility
Membrane Production
Peak Labour
65