STS was appointed for the Electrical & Instrumentation fit-out of two production buildings, MV Substations, utility buildings and generators in the new Biogen Biopharmaceutical campus. This Biogen facility in Luterbach, near Solothurn, is a state-of-the-art bio-medical facility that brings Biogen’s latest progress in biologics manufacturing technology to reality. The facility combines Biogen’s latest technology in terms of fed-batch cell culture technology and high-performance purification. In addition to production facilities, the plant will also house laboratories, office space, utility buildings and a warehouse.
The scope of work included the following:
- Complete electrical, instrument and BMS installation
- Provide and install primary/secondary containment systems
- Provide and install all power, control and signal cables
- Provide and install lighting fixtures and general services
- Install stick build instrumentation
- Provide and install of 5MVA generators
- Provide and install of transformers
- Provide and install of MV Switchgear
- Provide and install clocks
- Provide and install Earthing systems
- Provide testing and commissioning services
- Provide and install fire alarm cables and install detection devices
- Provide and install IT system cabling
- Install all BMS Instrumentation
- Assembly of vendor skids
- ESTI Certification and SINA sign off
Quick Facts
Duration
24 months
Team
Jacobs
Nature of Facility
Bio Pharma
Peak Labour
375