Biogen MV Generator Project, Luterbach, Switzerland

STS were appointed as the Design and Build contractor for 2no. New MV generators as part of the Biogen Next Generation Project.

The scope of this project included:

  • 2 no. 2MW containerized Diesel Generators complete with day tanks
  • Generators were stepped up from 400V to 16kV using separate 2.5MVA transformers.
  • The HV side of the transformers were connected to a new 16kV Switchboard with capacity for future generator connections
  • The new switchboard was connected to neutral earthing resisters fed through transformers for earthing the generators under various switching operations
  • The new 16kV board was also connected to two existing network supplies via existing 2no. 16kV existing switchboards
  • The generators were integrated to the plant BMS to provide fuel to the day tanks based on the fuel levels in the day tanks
  • Generator power outputs were also fed to the external network for monitoring
  • All Generator / Traffos / Switchgear / PMS / BMS Fuel systems commissioned

Quick Facts

Duration
18 months
Team
Jacobs
Peak Labour
14