A room with rows of white server racks in a data center.

Client Control Building & 3rd MV Transformer, Dublin, Ireland

STS Group provided the following scope of services with regards to our confidential clients control building & 4 bay transformer yard project.

The scope of this project included:

  • Purchase, Install, test 3rd 110kV / 20kV 63MVA transformer, metering equipment & NER
  • Design of power, control, protection & interconnecting cabling between transformer and protection panels and kiosk
  • Modifications and SAT to interface kiosk and protection panels
  • Supply the conductor to allow the earthing of HV side
  • Coordinate with ESBN, supply and install the HV cable connections (flexibles) from the Cable Sealing End to the transformer internal HV bushings
  • Provide the scaffolding in the cable pit to facilitate ESBN access for cable terminations
  • Terminate and test of MV cables
  • Supply, install, terminate and test of control cables and LV cables
  • Verify the new transformer is protected by the existing Lightning Protection system
  • Supply and install of containment & associated bracketry in CCB, Transformer bay & MV
  • Liaise with ESB metering department to schedule delivery to site of all free issue metering equipment and agree installation methodology
  • Install a free issue ESB metering and control cabling and mount associated equipment such as marshalling kiosks etc. as requested by ESB
  • Site Test all the equipment and Protective Relays
  • Civil works – tie into existing earth grid and erection of temporary site hoarding
  • Commission all elements of the system including interface commissioning with ESB

Quick Facts

Duration
13 months
Team
Confidential
Peak Labour
12